A, B, and C can do a piece of work in 36 days, 54 days and 108 days, respectively. They started the work together but A left 9 day

A, B, and C can do a piece of work in 36 days, 54 days and 108 days, respectively. They started the work together but A left 9 days after the start of the work and left 3 days before the work was completed. For how many days did C work?​

About the author
Sophia

2 thoughts on “A, B, and C can do a piece of work in 36 days, 54 days and 108 days, respectively. They started the work together but A left 9 day”

  1. Answer:

    60 days

    c worked for

    Step-by-step explanation:

    total work = 108 units

    efficiency of A = 3

    ” ” ” B = 2

    ” ” C= 1

    they worked together for 9 days

    wok done = (3+2+1)×9 = 54units

    work left = 54 units +3 days before b left the work so total work = 60

    days taken by c = 60 /1 =60