15. X number of men can finish a piece of work in 30
days. If there were 6 men more, the work could be
finished in 10 da

15. X number of men can finish a piece of work in 30
days. If there were 6 men more, the work could be
finished in 10 days less. What is the original number
of men?
(a) 10
(b) 11 (c) 12 (d) 15
(e) 13​​

About the author
Kylie

2 thoughts on “15. X number of men can finish a piece of work in 30<br />days. If there were 6 men more, the work could be<br />finished in 10 da”

  1. Solution:

    Given

    • X men take 30 days to complete a work.
    • 1 men will takes 30X days to complete then. (From the above relation).

    And,

    • If there were 6 more men, then number of men now is X + 6.
    • No. of days is 30 – 10 = 20 days.
    • X + 6 men take 20 days to complete.
    • 1 men will take (X + 6)20 days then..

    According To Sum

    [tex]→\;{\sf{30x = (x+6)20}}[/tex]

    [tex]→\;{\sf{30x = 20x+120}}[/tex]

    [tex]→\;{\sf{30x-20x = 120}}[/tex]

    [tex]→\;{\sf{10x = 120}}[/tex]

    [tex]→\;{\sf{x = \frac{120}{10}}}[/tex]

    [tex]→\;{\sf{x = 12}}[/tex]

    The Original Number of Men ◕➜ [tex]\Large{\red{\mathfrak{12\;✓}}}[/tex]