If 8 persons can weave 160 shawls in 5 days, how many shawls will be woven by 3 persons in14 days? About the author Arianna
Answer: Since, 8 persons in 5 days can weave 160 shawls. Then, 8 persons in 1 day can weave 160/5 shawls. So, 1 person in 1 day can weave 160/5*8 i.e. 4 shawls. Then, 3 persons in 1 day can weave 3*4 i.e. 12 shawls So, 3 persons in 14 days can weave 12*14 i.e 168 shawls. Reply
Answer:
12 days is the right answer
Answer:
Since, 8 persons in 5 days can weave 160 shawls.
Then, 8 persons in 1 day can weave 160/5 shawls.
So, 1 person in 1 day can weave 160/5*8 i.e. 4 shawls.
Then, 3 persons in 1 day can weave 3*4 i.e. 12 shawls
So, 3 persons in 14 days can weave 12*14 i.e 168 shawls.