Ayush and Rahul together complete a work in half of time of veer,while Ayush and veer together can complete same work in 1/3rd tim

By Rose

Ayush and Rahul together complete a work in half of time of veer,while Ayush and veer together can complete same work in 1/3rd time of Rahul .if they together complete a piece of work in 30days.then in how many days Rahul can alone complete the work.​

About the author
Rose

2 thoughts on “Ayush and Rahul together complete a work in half of time of veer,while Ayush and veer together can complete same work in 1/3rd tim”

  1. [tex]\large\underline{\sf{Solution-}}[/tex]

    Let

    • Time taken by Ayush alone to finish the work be ‘x’ days.
    • Time taken by Rahul alone to finish the work be ‘y’ days.
    • Time taken by Veer alone to finish the work be ‘z’ days.

    So,

    [tex]\rm :\longmapsto\: \: Ayush \: 1 \: day \: work \: = \dfrac{1}{x} [/tex]

    [tex]\rm :\longmapsto\: \: Rahul \: 1 \: day \: work = \dfrac{1}{y} [/tex]

    [tex]\rm :\longmapsto\: \: Veer \: 1 \: day \: work = \dfrac{1}{z} [/tex]

    Now,

    According to statement,

    • Ayush and Rahul together complete a work in half of time of veer.

    So, there 1 day work is

    [tex]\rm :\longmapsto\:\dfrac{1}{x} + \dfrac{1}{y} = \dfrac{2}{z} – – – (1)[/tex]

    Also, given that

    • Ayush and veer together can complete same work in 1/3rd time of Rahul.

    So, there 1 day work is

    [tex]\rm :\longmapsto\:\dfrac{1}{x} + \dfrac{1}{z} = \dfrac{3}{y} – – – (2)[/tex]

    Also, given that

    • They together complete a piece of work in 30days.

    So, there 1 day work is

    [tex]\rm :\longmapsto\:\dfrac{1}{x} + \dfrac{1}{y} + \dfrac{1}{z} = \dfrac{1}{30} [/tex]

    [tex]\rm :\longmapsto\:\dfrac{2}{z} + \dfrac{1}{z} = \dfrac{1}{30} \: \: \: \: \: \: \{using \: (1) \}[/tex]

    [tex]\rm :\longmapsto\:\dfrac{3}{z} = \dfrac{1}{30} [/tex]

    [tex]\bf\implies \:z \: = \: 90 – – – (4)[/tex]

    Now,

    On Subtracting equation (2) from equation (1), we get

    [tex]\rm :\longmapsto\:\dfrac{1}{y} – \dfrac{1}{z} = \dfrac{2}{z} – \dfrac{3}{y} [/tex]

    [tex]\rm :\longmapsto\:\dfrac{4}{y} = \dfrac{3}{z} [/tex]

    [tex]\rm :\longmapsto\:\dfrac{4}{y} = \dfrac{3}{90} \: \: \: \: \: \: \: \{ \because \: z = 90 \}[/tex]

    [tex]\rm :\longmapsto\:\dfrac{4}{y} = \dfrac{1}{30} [/tex]

    [tex]\bf\implies \:y = 120[/tex]

    [tex]\bf\implies \:Rahul \: alone \: take \: 120 \: days \: to \: finish \: the \: work.[/tex]

    Reply
  2. Answer:

    22.5 days

    Step-by-step explanation:

    let time required to do work by rahul is x

    by ayush is y

    by veer is z

    given x+y=z/2

    y+z=x/3..²

    and x+y+z=30 days

    from ²

    x+x/3=30

    4x/3=30

    4x=90

    x=90/4

    x=22.5

    hope my answer helps you

    Reply

Leave a Comment