As project manager, you have some ideas on how to recover a project that is falling behind schedule. Which action could you immediately take to get the project back on track? About the author Arya
[tex] \sf{Answer}[/tex] 7. Develop a new project plan. Stop/prevent all scope changes. Downward adjust the scope of work. Re-evaluate activities yet to be done. Develop a new viable/realistic schedule. Develop a risk management plan. Re-evaluate resource availability. Develop new project planning documents. [tex] \sf{Answer\:by\:UnicornRahuL}[/tex] Reply
[tex] \sf{Answer}[/tex]
7. Develop a new project plan.
[tex] \sf{Answer\:by\:UnicornRahuL}[/tex]
Answer:
Start with the solution you can authorize
Explanation: