A does a work in 80 days, B does the same work in 96 days. A+B+C can complete the work in 32 days. How much time will C take to do the work? About the author Eliza
Answer: 30 days Step-by-step explanation: hope it will help you if correct please mark me as brainliest Reply
Answer:
30 days
Step-by-step explanation:
hope it will help you if correct please mark me as brainliest