A contractor appoints 36 persons who complete 2/3 work in 16 days . To finish remaining work he appoints 12 more persons . In how

A contractor appoints 36 persons who complete 2/3 work in 16 days . To finish remaining work he appoints 12 more persons . In how many days remaining work will complete?​