A can finsh the work in 18 days ang B can do the work in half the time takes A what part of same work they can finish in a day About the author Remi
Answer: A can do the work = 18 days B can do the work = 18/2=9days (A+B)’s 1 day work =1/18 + 1/9 = 1/6 =>in 3 days = 3×1/6 = 1/2 work is completed Half work is the answer Reply
[tex]\boxed {\underline {\mathbb {COMPLETE\:QUESTION:-}}}[/tex] A can finish a work in 18 days and B can do the same work in half the time taken by A. Then working together what part of the same work can they finish in a day? [tex]\boxed {\underline {\mathbb {FINAL\:ANSWER:-}}}[/tex] [tex]\boxed {work\:compleated\:in\:a\:day=\frac{1}{6}}[/tex] [tex]\boxed {\underline {\mathbb {GIVEN:-}}}[/tex] A can finish the work in 18 days B can do the work in half the time takes A [tex]\boxed {\underline {\mathbb {TO\:FIND:-}}}[/tex] what part of the same work can they finish in a day [tex]\boxed {\underline {\mathbb {SOLUTION:-}}}[/tex] A can finish a work in 18 days. B can finish a work in 9 days. So In one day A can finish [tex]\frac{1}{18}[/tex] work. and In one day B can finish [tex]\frac{1}{9}[/tex] work So, working together the work can they finish in a day. W=A+B [tex]work=\frac{1}{18}+\frac{1}{9}\\\boxed {work=\frac{1}{6}}[/tex] ⇔⇔⇔⇔⇔⇔⇔⇔⇔⇔⇔⇔⇔⇔⇔⇔⇔⇔⇔⇔⇔⇔⇔⇔⇔⇔⇔⇔⇔⇔⇔ Reply
Answer:
A can do the work = 18 days
B can do the work = 18/2=9days
(A+B)’s 1 day work =1/18 + 1/9 = 1/6
=>in 3 days = 3×1/6 = 1/2 work is completed
Half work is the answer
[tex]\boxed {\underline {\mathbb {COMPLETE\:QUESTION:-}}}[/tex]
A can finish a work in 18 days and B can do the same work in half the time taken by A. Then working together what part of the same work can they finish in a day?
[tex]\boxed {\underline {\mathbb {FINAL\:ANSWER:-}}}[/tex]
[tex]\boxed {work\:compleated\:in\:a\:day=\frac{1}{6}}[/tex]
[tex]\boxed {\underline {\mathbb {GIVEN:-}}}[/tex]
[tex]\boxed {\underline {\mathbb {TO\:FIND:-}}}[/tex]
what part of the same work can they finish in a day
[tex]\boxed {\underline {\mathbb {SOLUTION:-}}}[/tex]
A can finish a work in 18 days.
B can finish a work in 9 days.
So In one day A can finish [tex]\frac{1}{18}[/tex] work.
and In one day B can finish [tex]\frac{1}{9}[/tex] work
So, working together the work can they finish in a day.
W=A+B
[tex]work=\frac{1}{18}+\frac{1}{9}\\\boxed {work=\frac{1}{6}}[/tex]
⇔⇔⇔⇔⇔⇔⇔⇔⇔⇔⇔⇔⇔⇔⇔⇔⇔⇔⇔⇔⇔⇔⇔⇔⇔⇔⇔⇔⇔⇔⇔