A can do a job in 4 1/2days, and B in 9 days.2.(1) How long will they take to complete the job together? (2) If they are paid Rs. 900 for the job, what will be each person’s share? About the author Sadie
Answer: Step-by-step explanation: Given :- A can do a job in = 4(1/2) Days. = (9/2) days. B can do same job in = 9 days. To find :- i) How long will they take to complete the job together ? ii) If they are paid 3900 for the job, what will be each person’s share ? Solution :- → LCM of (9/2) & 9 = 9 unit = Let Total work . So, → Efficiency of A = ( Total work) / (Total Time taken by A alone) = 9 / (9/2) = 9 * (2/9) = 2 Unit / day. → Efficiency of B = ( Total work) / (Total Time taken by A alone) = 9 / 9 = 1 Unit / day. Hence, → Efficiency of (A + B) = 2 + 1 = 3 unit / day. Therefore, → Time Taken by Both of Them To complete whole work = 9/3 = 3 Days..(Ans i) Hence, They take 3 days to complete the job together.. _________________ Now, we know That, Salary of workers is Given in The Ratio of Their Efficiency . → Efficiency of A = 2 unit/day. → Efficiency of B = 1 unit / day. So, → A share : B share = 2 : 1 Let A share is 2x & B share is x . Than, → 2x + x = 3900 → 3x = 3900 → x = 1300 Hence, → A share = 2x = 2*1300 = Rs.2600 → B share = x = 1*1300 = Rs.1300. (Ans ii) Therefore, Share of A & B are Rs,2600 & Rs.1300 Respectively. hope it helps plz mark as brainliest give it a thanks Reply
Answer:
Step-by-step explanation:
Given :-
A can do a job in = 4(1/2) Days. = (9/2) days.
B can do same job in = 9 days.
To find :-
i) How long will they take to complete the job together ?
ii) If they are paid 3900 for the job, what will be each person’s share ?
Solution :-
→ LCM of (9/2) & 9 = 9 unit = Let Total work .
So,
→ Efficiency of A = ( Total work) / (Total Time taken by A alone) = 9 / (9/2) = 9 * (2/9) = 2 Unit / day.
→ Efficiency of B = ( Total work) / (Total Time taken by A alone) = 9 / 9 = 1 Unit / day.
Hence,
→ Efficiency of (A + B) = 2 + 1 = 3 unit / day.
Therefore,
→ Time Taken by Both of Them To complete whole work = 9/3 = 3 Days..(Ans i)
Hence, They take 3 days to complete the job together..
_________________
Now, we know That, Salary of workers is Given in The Ratio of Their Efficiency .
→ Efficiency of A = 2 unit/day.
→ Efficiency of B = 1 unit / day.
So,
→ A share : B share = 2 : 1
Let A share is 2x & B share is x .
Than,
→ 2x + x = 3900
→ 3x = 3900
→ x = 1300
Hence,
→ A share = 2x = 2*1300 = Rs.2600
→ B share = x = 1*1300 = Rs.1300. (Ans ii)
Therefore, Share of A & B are Rs,2600 & Rs.1300 Respectively.
hope it helps
plz mark as brainliest
give it a thanks