A and B can do a piece of work in 16 days and A alone can do it in 24 days. How long will B alone take to complete the work? (a) 48 days (b) 43 days (c) 24 days (d) 12 days
So in 1 day they can do 1/16 of the work in 1 day. Similarly, A alone will do 1/24 of the work in 1 day. Therefore, B alone can do 1/16 – 1/24 = 1/48 of the work in 1 day, which means that B alone can do the complete work in 48 days.
Step-by-step explanation:
So in 1 day they can do 1/16 of the work in 1 day.
Similarly, A alone will do 1/24 of the work in 1 day.
Therefore,
B alone can do 1/16 – 1/24 = 1/48 of the work in 1 day,
which means that B alone can do the complete work in 48 days.
Answer:
A
Step-by-step explanation:
So in 1 day they can do 1/16 of the work in 1 day. Similarly, A alone will do 1/24 of the work in 1 day. Therefore, B alone can do 1/16 – 1/24 = 1/48 of the work in 1 day, which means that B alone can do the complete work in 48 days.