6 workmen prepare a shed in 40 days. How long will it take 20 men to make it?​

6 workmen prepare a shed in 40 days. How long will it take 20 men to make it?​

About the author
Peyton

1 thought on “6 workmen prepare a shed in 40 days. How long will it take 20 men to make it?​”

  1. Answer:

    12 days

    Step-by-step explanation:

    6 men do in 40 days

    let time taken by 20 men = X

    so 6×40 = 20 X

    6×40÷20 = X

    12 = X