A can do a piece of work in 20 days and B can do it in 12 days. B
worked for 9 days and quit. In how many days can A alone fi

A can do a piece of work in 20 days and B can do it in 12 days. B
worked for 9 days and quit. In how many days can A alone finish
the remaining work?​

About the author
Josephine

1 thought on “A can do a piece of work in 20 days and B can do it in 12 days. B<br />worked for 9 days and quit. In how many days can A alone fi”

  1. B’s 9 day’s work = ( 1/12×9) =3/4

    Remaining work = 1−3/4=1/4

    1/20 work is finished by A in 1 day.

    1/4 work is finished by A in (20× 1/4) =5 days