in a company 25 workers can compete a work in 12 days in how many days will 50 workers​

By Ayla

in a company 25 workers can compete a work in 12 days in how many days will 50 workers​

About the author
Ayla

2 thoughts on “in a company 25 workers can compete a work in 12 days in how many days will 50 workers​”

  1. Answer:

    Given :

    Twenty five workers were employed to complete a compound wall in 12 days. Five workers left after working for 4 days. The remaining 20 workers completed the work.

    To Find:

    In how many days the total job was completed?

    Solution:

    25 workers completed work in days = 12

    25 workers 1 day work =1/12

    25 workers 4 days work = 4/12

    Remaining work =1 – 4/12

    25 workers complete work in days = 12

    1 worker complete work in days = 12 x 25

    20 workers complete work in days = 12 x 25/20

    20 workers complete work in days = 12 x 25/20 x 8/12 =10

    No. of days required to complete work = 10+4=14 days

    Hence the total job was completed in 14 days