56 workers can finish a piece of work in 14 days. If the work is to be completed in 8 days, then
how many extra workers are r

56 workers can finish a piece of work in 14 days. If the work is to be completed in 8 days, then
how many extra workers are required?
(a) 36
(b) 48
(c) 44
(d) 42
(e) 32​

About the author
Rylee

2 thoughts on “56 workers can finish a piece of work in 14 days. If the work is to be completed in 8 days, then<br />how many extra workers are r”

  1. Here men required to perform a work is M and days required is D. As the quantity of the job or work is constant – Number of days D is inversely proportional to men to be engaged M.

    D ∝ 1/M , when work is same or constant

    D= K/M [K is proportionality constant]

    M*D = K …..(1)

    When M = 56 , D=14, Therefore K= 56*14

    From (1) M* D = 56*14, When D=8

    M*8 = 56*14

    M= 56*14/8 = 98 , To complete the same work in 8 days , additional man power required is

    98 -56 = 42

    Additional men required is 42

    Reply
  2. Answer:

    (a) 36

    Step-by-step explanation:

    56/14 = x/8

    x = 56*8/14

    therefore, x= 36