19. 20 men can do a work in 20 days. How many more men are needed to complete the
work in 5 days?​

19. 20 men can do a work in 20 days. How many more men are needed to complete the
work in 5 days?​

About the author
Ariana

1 thought on “19. 20 men can do a work in 20 days. How many more men are needed to complete the<br />work in 5 days?​”

  1. Explanation:

    Let the required number of men be x.

    Number of men ㅤ ㅤ20 ㅤ ㅤx

    Number of days ㅤ ㅤ20 ㅤ ㅤ 5

    More the number of men, less the number of days required. Therefore, this is a case of inverse variation

    By inverse variation xy = k,

    [tex]20 \times 20 = x \times 5[/tex]

    [tex]x = \frac{20 \times 20}{5} [/tex]

    [tex] x = 20 \times 4[/tex]

    [tex]x = 80[/tex]

    Therefore, 80 men are required to finish the work in 5 days.

    Answer: 80 men