2 boys and 6 girls complete a certain piece of work in 4 days. But 1 boy and 5 girls complete the same in 6 days. Find the number of days re- quired to complete the same work for each boy and each girl. About the author Mary
Answer: Time taken by one boy to complete the work=16days Time taken by one girl to complete the work=48days Step-by-step explanation: 2+6=1 x y 4 2u+6v=1/4 (i) 1+5=1 x y 6 2+10=1 x y 3 2u+10v=1/3 (ii) on subtracting (i) from (ii), we get: 4v=1/12 v=1/48 or y=48 Putting the value of y in (i), we get: x=16 Reply
Answer:
Time taken by one boy to complete the work=16days
Time taken by one girl to complete the work=48days
Step-by-step explanation:
2+6=1
x y 4
2u+6v=1/4 (i)
1+5=1
x y 6
2+10=1
x y 3
2u+10v=1/3 (ii)
on subtracting (i) from (ii), we get:
4v=1/12
v=1/48
or y=48
Putting the value of y in (i), we get:
x=16
Answer:
1 Boy and 5 Girls completed the days are 4 days and or 3 days okk