10) 25 farmers take 12 days to plough 15 bighas of land. Let’s find, how many bighas
of land can be ploughed by 30 farmers in

10) 25 farmers take 12 days to plough 15 bighas of land. Let’s find, how many bighas
of land can be ploughed by 30 farmers in 16 days.​