1. Santosh requires 3 days more than Deepak to complete a work. If they wetogether, the work can be completed in 2 days. Find the number of dayrequired for each of them to complete the work. About the author Iris
Answer: Let Deepak complete a work in x day. Santosh work be (x+3) days therefore, work done by deepak in one day will be 1/x and work done by santosh be 1/x+3. Work done by both of them in 2 days = 1/2 A.T.Q 1/x + 1/x+3 = 1/2 therefore by this we will get x=3 or x= -2 but the number of days is not negative so we will take x =3 and x+3 = 3+3=6 therefore deepak completes the work in 3 days and santosh in 6 days . Reply
Answer:
Let Deepak complete a work in x day.
Santosh work be (x+3) days
therefore, work done by deepak in one day will be 1/x and work done by santosh be 1/x+3.
Work done by both of them in 2 days = 1/2
A.T.Q
1/x + 1/x+3 = 1/2
therefore by this we will get x=3 or x= -2
but the number of days is not negative
so we will take
x =3 and x+3 = 3+3=6
therefore deepak completes the work in 3 days and santosh in 6 days .